Construction Requirements BAL-40 Building Codes & Rules


- Comply with Bushfire Construction Requirements with Tools™: BAL-40 requirements, fire danger insights, & detailed guidance for walls, roof, guttering & more!


AS 3959:2018, 3.2.1

Wall & Openings Fire Separated from GarageAS 3959:2018, 3.2.1

  • Only if the attached Garage is not constructed to BAL requirements

Services


  • Metal for Plumbing above ground[1]
  • Power lines to be buried[2]


Utility Service RULES


NCC 2022 V3


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



NSW RFS 2019 PBP, 5.3.3

NSW RFS 2019 PBP, 7.4

NSW RFS 2019 PBP, 5.3.3

NSW RFS 2019 PBP, 7.4

AS 3959:2018, 8.8

AS 3959:2018, 8.8

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

  • Building elements within Bushfire-prone Areas to be Bushfire Attack Resistant to the NCCNSW RFS 2019 PBP, 5.3.3NSW RFS 2019 PBP, 7.4
  • Water SupplyNSW RFS 2019 PBP, 5.3.3
  • Metal above-ground Water Pipes, Taps, Storage Tank
  • Fire Hydrants prohibited on road carriageway
  • Gas ServicesNSW RFS 2019 PBP, 7.4
  • Steel or Copper above-ground Gas Pipes
  • ≥ 900mm Wall thickness (follow local gas provider rules or whichever is greater)
  • ≥ 400mm extension inside the building
  • ≥ 100mm underground extension
  • Refer to local Gas regulations for additional information
  • Bottled Gas InstallationAS 3959:2018, 8.8AS 3959:2018, 8.8
  • Shield or locate away from building
  • Away from flammable materials
  • Connections are made of Metal
  • Polymer-sheated flexible gas supply lines are prohibited
  • Electricity ServicesNCC 2022 Vol 1, G5D1NCC 2022 Vol 2, H7D4
  • Power lines to be buried
  • Overhead lines
  • ≥ 30m Pole spacing
  • Refer to ISSC3 for Managing Vegetation near Power lines

AS 3959:2018, 8.8

NSW RFS 2019 PBP, 5.3.3

Bushfire shutter (optional)

Garage door

AS 3959:2018, 3.2.3 (a)

> 6mAS 3959:2018, 3.2.3 (a)

NSW RFS 2019 PBP, 7.6

Fencing

Penetrations


  • Sealed with non-combustible materials[1]


Penetrations RULES


NCC 2022 V3


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.6.5 (a)

AS 3959:2018, 8.6.5 (b)

AS 3959:2018, 8.6.5 (d)

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

Screen RULES


NCC 2022 V2


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 3.6.1

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

AS 3959:2018, 8.6.5 (a)

Vent & Weepholes


  • Use rust-proof Screens for the Vents[1]


Door RULES


NCC 2022 V3


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.5.4 (b) (i) (A)

AS 3959:2018, 8.5.4 (b) (i) (B)

AS 3959:2018, 8.5.4 (b) (i) (C)

AS 3959:2018, 8.5.4 (b) (ii)

AS 3959:2018, 8.5.4 (b) (vii)

AS 3959:2018, 8.5.4 (b) (v)

AS 3959:2018, 8.5.4 (b) (iv)

AS 3959:2018, 8.5.4 (a)

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

Vent & Weepholes RULES


NCC 2022 V3


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.4.3

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

AS 3959:2018, 8.4.3

Floor & Balcony


  • Use non-combustible materials if unenclosed[1]


Screen RULES


NCC 2022 V2


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 3.6.1

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

Wall Construction RULES


NCC 2022 V4


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.4.1 (a)

AS 3959:2018, 8.4.1 (b) (i)

AS 3959:2018, 8.4.1 (c)

NSW RFS 2019 PBP, 7.5.4

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

NSW RFS 2019 PBP, 7.4

Guttering & Downpipes


  • Fully Flashed & non-combustible Box Gutter[1]
  • Turn Sarking into Gutter[2]


Gutter & Downpipes RULES


NCC 2022 V3


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.6.7

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

AS 3959:2018, 8.6.7

AS 3959:2018, 8.6.2

Bushfire Shutter


  • Made of materials resistant to combustion[1]
  • ≤ 2mm Aperture Gaps, Slots or Screen[2]


Bushfire Shutter MATERIALS


NCC 2022 V3


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.5.1

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

Screen RULES


NCC 2022 V2


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 3.6.1

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

Bushfire Shutter RULES


NCC 2022 V3


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 3.7 (a)

AS 3959:2018, 3.7 (b)

AS 3959:2018, 3.7 (d)

AS 3959:2018, 3.7 (e)

AS 3959:2018, 3.7 (f)

AS 3959:2018, 3.7 (g)

AS 3959:2018, 3.7 (g)

AS 3959:2018, 3.7

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

AS 3959:2018, 8.5.1

AS 3959:2018, 3.6.1

Decks & Landing


  • Enclosing the entire Subfloor will be protected[1]
  • Non-combustible material[2]


Decks & Landings RULES


NCC 2022 V3


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.7.1

AS 3959:2018, 8.7.2.1

AS 3959:2018, 8.7.3

AS 3959:2018, 8.7.4

AS 3959:2018, 8.7.5

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

  • Building elements within Bushfire-prone Areas to be Bushfire Attack Resistant to the NCCAS 3959:2018, 8.7.1AS 3959:2018, 8.7.2.1
  • Decks & similar structuresAS 3959:2018, 8.7.3
  • No gaps allowed between Deck boards
  • Subfloor enclosure not mandatory
  • Enclosed SubfloorAS 3959:2018, 8.7.4
  • Enclosing the entire Subfloor will be protected
  • Walls to same rules as building, & openings protected by 
  • ≤ 2mm aperture screen of corrosion-resistant materials
  • No requirements for Support & Framing
  • Unenclosed Subfloor AS 3959:2018, 8.7.5
  • Non-combustible Support & Framing
  • Handrails & BarriersNCC 2022 Vol 1, G5D1
  • ≤ 125mm from combustible Wall or Glazing
  • Non-combustible material required
  • ≥ 125mm from Building
  • No requirement
  • Veranda PostsNCC 2022 Vol 2, H7D4
  • Non-combustible material
  • Materials constructed to AS 1530.8.1

AS 3959:2018, 8.7.2.4 (a)

NSW RFS 2019 PBP, 7.4

Doors, Frames, Sidelights


  • Doors with Seals all round[1]
  • ≥ 35mm thk non-combustible Panels[2]
  • ≥ 6mm Toughened Glazing[3]
  • Metal framing materials[4]


Door RULES


NCC 2022 V3


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.5.4 (b) (i) (A)

AS 3959:2018, 8.5.4 (b) (i) (B)

AS 3959:2018, 8.5.4 (b) (i) (C)

AS 3959:2018, 8.5.4 (b) (ii)

AS 3959:2018, 8.5.4 (b) (vii)

AS 3959:2018, 8.5.4 (b) (v)

AS 3959:2018, 8.5.4 (b) (iv)

AS 3959:2018, 8.5.4 (a)

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

Screen RULES


NCC 2022 V2


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 3.6.1

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

AS 3959:2018, 8.5.4 (b) (i) (B)

AS 3959:2018, 8.5.4 (b) (iv)

AS 3959:2018, 8.5.4 (b) (iii)

AS 3959:2018, 8.5.4 (b) (v)

Walls


  • Non-combustible materials[1]
  • Seal or screen all openings[2]


Jointing RULES


NCC 2022 V3


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.4.2

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

Wall Construction RULES


NCC 2022 V4


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.4.1 (a)

AS 3959:2018, 8.4.1 (b) (i)

AS 3959:2018, 8.4.1 (c)

NSW RFS 2019 PBP, 7.5.4

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

Vent & Weepholes RULES


NCC 2022 V3


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.4.3

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

AS 3959:2018, 8.4.1 (a)

AS 3959:2018, 8.4.3

AS 3959:2018, 3.2.1 (a)

Wall

AS 3959:2018, 3.2.1 (a)

Self-closing

Fire Door

AS 3959:2018, 3.2.1 (a)

Permanently Closed

Window

Garage & Carport Under


  • All elements to BAL-40 Rules[1], or
  • Fire separated


Fire Wall RULES


NCC 2022 V1


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 3.2.2 (a)

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

AS 3959:2018, 3.2.2

AS 3959:2018, 3.2.2 (b)

AS 3959:2018, 3.2.2 (a)

Eaves & Fascias


  • Gables need to be built same as Fire Walls[1]
  • Eaves penetrations sealed[2]
  • Seal Joints[3]


Screen RULES


NCC 2022 V2


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 3.6.1

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

Eave & Fascia RULES


NCC 2022 V3


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.6.6 (c)

AS 3959:2018, 8.6.6 (b)

AS 3959:2018, 8.6.6 (a)

AS 3959:2018, 8.6.6 (f)

NSW RFS 2019 PBP, 7.5.2

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

AS 3959:2018, 8.6.6 (a)

AS 3959:2018, 8.6.6 (d)

AS 3959:2018, 8.6.6 (f)

Attached Structure


  • Follow adjacent structure requirements[1], or
  • Main Building is protected by
  • ≥ –/60/60 FRL Non-loadbearing Wall[2]
  • ≥ 60/60/60 FRL Loadbearing Wall[3]
  • –/60/30 FRL Self-closing Fire Door[4]
  • –/60/– FRL permanently closed Window[5]


Attached Structure RULES


NCC 2022 V3


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 3.2.1

AS 3959:2018, 3.2.1 (a)

AS 3959:2018, 3.2.1 (a)

AS 3959:2018, 3.2.1 (a) (i)

AS 3959:2018, 3.2.1 (a) (ii)

AS 3959:2018, 3.2.1 (b)

AS 3959:2018, 3.2.1 (b) (i)

AS 3959:2018, 3.2.1 (b) (iii)

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

AS 3959:2018, 3.2.1

AS 3959:2018, 3.2.1 (a)

AS 3959:2018, 3.2.1 (a)

AS 3959:2018, 3.2.1 (a) (i)

AS 3959:2018, 3.2.1 (a) (ii)

Skylights


  • ≤ 18° Roof pitch for exterior glazing[1]
  • -/30/- FRL for glazed assemblies[2]
  • Corrosion-resistant Steel or Bronze Frames[3]
  • Non-combustible sealant & conduit for penetrations[4][5]


Screen RULES


NCC 2022 V2


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 3.6.1

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

Skylight RULES


NCC 2022 V3


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.6.5 (b)

AS 3959:2018, 8.6.5 (c)

AS 3959:2018, 8.6.5 (c)

AS 3959:2018, 8.6.5 (c)

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

AS 3959:2018, 8.6.5 (c)

AS 3959:2018, 8.6.5 (c)

AS 3959:2018, 8.6.5 (a)

AS 3959:2018, 8.6.5 (d)

AS 3959:2018, 8.6.5 (b)

Roofing


  • Non-combustible materials[1]
  • Full layer of Sarking[2][3]
  • Seal Joints[4]
  • Vents fitted with Ember Guards[5]


Roofing RULES


NCC 2022 V1


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.6.1 (a)

AS 3959:2018, 8.6.1 (b)

AS 3959:2018, 8.6.1 (b)

AS 3959:2018, 8.6.1 (c)

AS 3959:2018, 8.6.1 (d)

Screen RULES


NCC 2022 V1


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 3.6.1

  • Building elements within Bushfire-prone Areas to be Bushfire Attack Resistant to NCC Specification 1, NCC Part G5, & AS 3959
  • Corrosion-resistant Steel or Bronze Perforated Sheet or Mesh with
  • ≤ 2mm aperture size or openingAS 3959:2018, 3.6.1

Tiled Roof RULES


NCC 2022 V3


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.6.2

AS 3959:2018, 8.6.2 (b)

AS 3959:2018, 8.6.2 (b)

AS 3959:2018, 8.6.2 (a)

Eave & Fascia RULES


NCC 2022 V2


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.6.6 (c)

AS 3959:2018, 8.6.6 (b)

AS 3959:2018, 8.6.6 (a)

AS 3959:2018, 8.6.6 (f)

NSW RFS 2019 PBP, 7.5.2

Metal Sheet Roof RULES


NCC 2022 V2


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.6.3 (a)

AS 3959:2018, 8.6.3 (b)

  • Building elements within Bushfire-prone Areas to be Bushfire Attack Resistant to NCC Specification 1, NCC Part G5, & AS 3959
  • Roofs entirely sarked, exceptAS 3959:2018, 8.6.3 (a)
  • If with Insulation with foil underneath blankets allowed over Battens
  • Gaps sealed at Edges, Hips, & Ridges withAS 3959:2018, 8.6.3 (b)
  • Mesh or perforated sheet screened
  • Mineral Wool
  • Non-combustible materials

Penetrations RULES


NCC 2022 V1


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.6.5 (a)

AS 3959:2018, 8.6.5 (b)

AS 3959:2018, 8.6.5 (d)

Skylight RULES


NCC 2022 V1


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.6.5 (b)

AS 3959:2018, 8.6.5 (c)

AS 3959:2018, 8.6.5 (c)

AS 3959:2018, 8.6.5 (c)

Gutter & Downpipes RULES


NCC 2022 V2


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.6.7

  • Building elements within Bushfire-prone Areas to be Bushfire Attack Resistant to NCC Specification 1, NCC Part G5, & AS 3959
  • Gutter materials to be non-combustibleAS 3959:2018, 8.6.7
  • Box Gutter flashed at Roof junction
  • Valley Leaf Guards, optional
  • No requirement for Downpipes

AS 3959:2018, 8.6.2

AS 3959:2018, 8.6.1 (a)

AS 3959:2018, 8.6.3 (a)

AS 3959:2018, 8.6.1 (b)

AS 3959:2018, 8.6.1 (c)

Detached Structure


  • > 6m separation[1], or
  • Same Fire-resisting construction[2] , or
  • Main Building protected by
  • ≥ –/60/60 FRL Non-loadbearing Wall[3]
  • ≥ 60/60/60 FRL Loadbearing Wall[4]
  • –/60/30 FRL Self-closing Fire Door[5]
  • –/60/– FRL permanently closed Window[6]


Detached Structure RULES


NCC 2022 V3


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 3.2.3 (a)

AS 3959:2018, 3.2.3 (b)

AS 3959:2018, 3.2.3 (b)

AS 3959:2018, 3.2.3 (b) (i)

AS 3959:2018, 3.2.3 (b) (ii)

AS 3959:2018, 3.2.3 (c)

AS 3959:2018, 3.2.3 (c)

AS 3959:2018, 3.2.3 (b) (ii)

AS 3959:2018, 3.2.3 (b) (iii)

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

AS 3959:2018, 3.2.3 (a)

AS 3959:2018, 3.2.3

AS 3959:2018, 3.2.3 (b)

AS 3959:2018, 3.2.3 (b)

AS 3959:2018, 3.2.3 (b) (i)

AS 3959:2018, 3.2.3 (c) (ii)

Windows & Glazed Doors


  • ≥ 6mm Toughened Glazing[1]
  • ≤ 5 Flammability Index to seals[2]
  • Fixed & operable parts to be screened[3]


Screen RULES


NCC 2022 V2


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 3.6.1

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

Window RULES


NCC 2022 V3


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.5.3 (b) (iii)

AS 3959:2018, 8.5.3 (b) (iv)

AS 3959:2018, 8.5.3 (b) (v)

AS 3959:2018, 8.5.3 (b) (i)

AS 3959:2018, 8.5.3 (b) (ii)

AS 3959:2018, 8.5.3 (a)

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

AS 3959:2018, 8.5.3 (b) (iii)

AS 3959:2018, 8.5.3 (b) (iv)

AS 3959:2018, 8.5.3 (b) (v)

Garage Doors


  • Non-combustible materials[1]
  • ≤ 5 Flammability Index to seals[2]
  • Ventilation Slots are prohibited[3]


Garage Doors RULES


NCC 2022 V1


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.5.6 (a)

AS 3959:2018, 8.5.6 (c)

AS 3959:2018, 8.5.6 (e)

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

AS 3959:2018, 8.5.6 (a)

AS 3959:2018, 8.5.6 (c)

AS 3959:2018, 8.5.6 (e)

Sarking


  • ≤ 5 Flammability Index[1]
  • Roofs need a full layer of Sarking[2][3]


Sarking RULES


NCC 2022 V3


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 3.10

AS 3959:2018, 3.10

NSW RFS 2019 PBP, 7.5.2

NSW RFS 2019 PBP, 7.5.2

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

AS 3959:2018, 8.6.2

AS 3959:2018, 8.6.3 (a)

AS 3959:2018, 3.10

Verandah or Awning Roof


  • Roof Space component[1]
  • Follow Main Roof requirements
  • As a separate feature[2]
  • Covering materials to be non-combustible
  • Combustible elements to be lined with[3]
  • ≥ 6mm Fibre-cement or
  • AS 1530.8.1 compliant material


Tiled Roof RULES


NCC 2022 V1


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.6.2

AS 3959:2018, 8.6.2 (b)

AS 3959:2018, 8.6.2 (b)

AS 3959:2018, 8.6.2 (a)

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

Metal Sheet Roof RULES


NCC 2022 V1


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.6.3 (a)

AS 3959:2018, 8.6.3 (b)

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

External Roofing RULES


NCC 2022 V1


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.6.4 (a)

AS 3959:2018, 8.6.4

AS 3959:2018, 8.6.4 (b) (ii)

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

Post RULES


NCC 2022 V1


All Building Classes


NCC 2022 G5, H7D4, & S1

[2019 G5, 3.10.5, Sch 5]


May 2023



AS 3959:2018, 8.7.5

NCC 2022 Vol 1, G5D1

NCC 2022 Vol 2, H7D4

AS 3959:2018, 8.6.4 (a)

AS 3959:2018, 8.6.4 (b)

AS 3959:2018, 8.6.4 (b) (ii)