Concrete Overview Building Codes & Rules


- Get concrete right the first time. Use our Concrete Overview Tool™ to follow key NCC rules for testing, pouring, vibrating, and curing concrete safely.


Industry Recommendation

Industry Recommendation

Industry Recommendation

AS 3600:2018, 19.1

NCC 2022 HP, 4.2.8

Pre-Pour PreparationIndustry Recommendation

  • Site cleared, levelled, & compacted per soil classification
  • Verify formwork stability, dimensional conformity & _ elevation accuracy
  • Reinforcement placed with correct cover support
  • Conduct reinforcement inspection hold points (position, tying, cleanliness, cover) to prevent damage
  • Check placement of construction, movement & isolation jointsIndustry Recommendation
  • Vapour barrier correctly installed as per NCC requirementsIndustry Recommendation


Pour & PlacementAS 3600:2018, 19.1

  • Confirm delivery docket & concrete mix design conform to Engineer's Specifications
  • Place concrete vertically & evenly close to its final position to prevent segregation
  • Shovel concrete into place & avoid letting it flow
  • For deep forms, prevent concrete from ricocheting off rebar/forms by controlling drop height
  • Ensure formwork & reinforcement is not displaced & damaged during pour
  • Cover fresh concrete with secured impermeable sheeting & manage surface runoff to prevent contact with the rainwater
  • Avoid concreting during or before anticipated heavy rain


Vibration & CompactionNCC 2022 HP, 4.2.8

  • Vibration removes air voids, compacting concrete to enhance strength & durability
  • Initial vibration liquefies the concrete, allowing for efficient void release
  • Optimal compaction is achieved when surface air bubbles cease to appear
  • Proper re-vibration can improve bond & finish, but excessive vibration leads to segregation & honeycombing

Concrete Testing


  • Compressive Strength Test[1]
  • Conducted at 7, 14, & 28 days
  • 1 test per 20 to 50m³ of concrete placed
  • Slump Test[2]
  • Performed at the start of each pour


Other Methods of Fresh Concrete Testing


NCC 2022 V1


Industry Recommendation

  • Different routine tests on fresh concrete assess its consistency, workability & measure distinct parameters, results are not directly comparable, & one test's outcome cannot validate compliance based on another's specificationIndustry Recommendation

Slump Test COMPLIANCE


NCC 2022 V1


AS 1379:2007, 5.2.2

AS 1379:2007, 5.2.1

AS 1379:2007, 4.2.3

AS 1379:2007, 5.2.4

AS 1379:2007, 5.2.3

Other Methods of Hardened Concrete Testing


NCC 2022 V1


Industry Recommendation

  • Various tests from simple to complex are performed on hardened concrete to assess its properties & service performance, utilizing both non-destructive & destructive methods with varying timeframesIndustry Recommendation

Slump Test REQUIREMENTS


NCC 2022 V1


Manufacturer's Requirement

Manufacturer's Requirement

Manufacturer's Requirement

Manufacturer's Requirement

Manufacturer's Requirement

Manufacturer's Requirement

  • Testing carried out in accordance to AS 1012.3.1Manufacturer's Requirement
  • Determines the slump consistency & workability of fresh concrete, typically for mixes with nominal aggregate size ≤ 40mmManufacturer's Requirement
  • ApparatusManufacturer's Requirement
  • Slump Cone: 200mm base, 100mm top, 300mm height, smooth, non-absorbent, unreactive & rigid ≥ 1.5mm thk galvanised steel sheet
  • Rod: Ø 16mm, 600mm long, rounded end
  • Scoop: For placing concrete
  • Base plate: Smooth, horizontal, non-vibrating
  • Measuring device: Ruler or tape measure
  • ProcedureManufacturer's Requirement
  • Clean/moisten cone & base plate
  • Fill cone in 3 equal layers, overfilling the top
  • Rod each layer 25 times with the rounded tamping rod to ensure full compaction & overfill the top layer
  • Strike off excess concrete flush with the cone's top
  • Lift cone vertically 3 ±1 seconds without displacement
  • Immediately measure slump (300mm - specimen height) to nearest 5mm (for ≤100mm) or 10mm (for >100mm)
  • Test ValidityManufacturer's Requirement
  • Entire procedure must be completed within 3 minutes
  • Invalid if specimen collapses or shear
  • RecordManufacturer's Requirement
  • Identification of Test Specimen
  • Date
  • Measured Slump (mm)
  • Shear or Lateral Collapse

Concrete Test Frequency & Compliance


NCC 2022 V1


Industry Recommendation

Industry Recommendation

Industry Recommendation

Testing for QualityIndustry Recommendation

  • Detailed protocols for concrete strength, workability & durability testing to AS 1012 Series
  • Samples taken during mixing, pouring, & curing, then verifying to AS 3600 for compliance
  • Generates performance data of Concrete to ensure long-term structural integrity

FrequencyIndustry Recommendation

  • Large & complex projects demand higher testing frequency
  • High-strength or specialized concrete mixes require more frequent checks
  • Extreme temperatures needs increased testing due to their impact on curing & strength
  • High-risk structural elements mandate more stringent testing protocols
  • Air content & temperature tests may be required for specific environmental conditions, with frequencies determined by project needs

ComplianceIndustry Recommendation

  • Obtain representative concrete samples from the batch following AS 1012 procedures
  • Use calibrated & maintained testing equipment
  • Ensure all tests are performed by trained & qualified personnel proficient in AS 1012 series
  • Maintain comprehensive records including test results, sample IDs, dates, & conditions, for quality assurance & compliance verification
  • Adhere strictly to project-specific testing requirements detailed in the concrete mix design & contract to meet performance standards

Compressive Strength Test REQUIREMENTS


NCC 2022 V1


Manufacturer's Requirement

Manufacturer's Requirement

Manufacturer's Requirement

Manufacturer's Requirement

Manufacturer's Requirement

Manufacturer's Requirement

Manufacturer's Requirement

Manufacturer's Requirement

  • Measures the ability of concrete to withstand compressive forcesManufacturer's Requirement
  • Test carried out according to AS 1012.9Manufacturer's Requirement
  • Test SpecimensManufacturer's Requirement
  • Concerete prepared per AS 1012.8 or AS 1012.14 for cores
  • Age at testing, (e.g., 7, 14 & 28 days)
  • Cylinder SizeManufacturer's Requirement
  • Ø100mm × 200mm (H) for ≤ 20mm aggregate size
  • Ø150mm × 300mm (H) for ≤ 40mm aggregate size
  • ApparatusManufacturer's Requirement
  • Compression Testing Machine calibrated per AS 2193
  • ProcedureManufacturer's Requirement
  • Place specimen centrally on lower plate
  • Align with spherical seating block
  • Apply continuous, uniform load
  • Maintain specified stress rate (e.g., 0.2 MPa/s to 0.4 MPa/s)
  • Record maximum load (kN) at failure
  • Note type of failure
  • Determine Compressive Strength (MPa)Manufacturer's Requirement
  • Computed result of Compressive Strength must be verified by the Structural Engineer
  • RecordManufacturer's Requirement
  • Specimen ID, age, dimensions
  • Maximum load
  • Compressive Strength
  • Type of fracture
  • Any deviations from standard

Manufacturer's Requirement

Manufacturer's Requirement

Joints


  • Allow for movement in a building[1]
  • Separate between different pours[2]


Concrete JOINTS


NCC 2022 V3


All Building Classes


NCC 2022, H1D1 & 4.2.10 [2019 3.2.3.1]


May 2023



AS 3600:2018, 19.1.2

AS 3600:2018, 19.1.3

AS 3600:2018, 19.1.4

NCC 2022 HP, 4.2.10

  • Concrete must comply with NCCAS 3600:2018, 19.1.2
  • Construction JointsAS 3600:2018, 19.1.3
  • Allows easier concrete placement & finishing
  • Junction between different stages of pours
  • These do not allow movement
  • Located in areas that are not critical
  • Designed based on specific construction practices & Concrete placement requirements
  • Placed in areas of low shear force & minimal visibility
  • Spacing depends on placement rate, finishing needs, & unexpected suspension
  • Movement JointsAS 3600:2018, 19.1.4
  • Allows for differential movement throughout the building's life without compromising the overall structure
  • Control movement at the Joint & cracking at specific locations
  • Spacing is crucial & considers various factors like shrinkage, temperature, & prestress (if applicable)
  • Contraction Joints
  • Controls cracking due to concrete shrinkage from curing
  • Joint Fillers & SealantsNCC 2022 HP, 4.2.10
  • Fillers inserted compressed, either during concrete placement or after hardening
  • Sealants provide additional functionalities
  • Weatherproofing
  • Acoustic insulation
  • Fire resistance
  • Preventing material ingress
  • Fillers & Sealants can be used in a single Joint
  • Designed to prevent dirt or other materials from entering & hindering movement
  • Infill materials & Concrete edges need to be strong enough to prevent damage for Joints with anticipated loading

AS 3600:2018, 19.1.3.1 (c)

AS 3600:2018, 19.1.2.1

NCC 2022 HP, 4.2.2

NCC 2022 HP, 4.2.5

NCC 2022 HP, 4.2.11

On-site Compliance per NCC requirements

  • Site ClassificationNCC 2022 HP, 4.2.2
  • Site has been classified in accordance with AS 2870
  • Helps identify common soil types
  • For more complex sites, use AS 2870 or ask a Structural/Geotechnical Engineer
  • Foundations for Footings & SlabsNCC 2022 HP, 4.2.5
  • For Slabs, Internal Beams, Load Support Areas: ≥ 50 kPa Founded on natural soil
  • For Edge Beams: ≥ 50 kPa On natural soil
  • For Pad Footings, Strip Footings, Unconnected Edge Beams: ≥ 100 kPa On natural soil
  • Steel ReinforcementNCC 2022 HP, 4.2.11
  • Such welded wire mesh (square mesh), trench mesh, steel reinforcing bars
  • Always check lap lengths match the drawings or standard tables

Waffle Raft Footing

Stiffened Raft Footing

Footing Slab

Concrete Curing

Wall Pour Joints


  • To comply with AS 3610.1 Formwork for Concrete
  • Indented or disguised control & Construction Joints for vertical surfaces


Indented Horizontal Pour Joint


NCC 2022 V3


Industry Recommendation

  • Crucial for managing concrete's natural movement due to factors like temperature changes & shrinkageIndustry Recommendation
  • Rebate to emphasise Joints
  • Use pre-formed Foam Strip on the Joint between Plywood sheets
  • Prevents moisture penetration
  • Averts Cement Grout leakage
  • Use Fibreglass & form liners
  • For textured form Joints
  • For complex shapes & profiles
  • To comply with AS 3610.1 Formwork for Concrete
  • Indented or disguised control & Construction Joints for vertical surfaces

Concrete Surface Finish

Threshold

Soil Classification

Formwork

Minimum Cover


  • Thickness of Concrete around Steel reinforcement to protect from corrosion[1]
  • Ensure formwork is completelty filled large voids at the edges[2]


Concrete COVER


NCC 2022 V5


All Building Classes


NCC 2022 4.2.11 [2019 3.2.3.2]


May 2023



AS 3600:2018, 4.10.3.2

AS 3600:2018, 4.3.1 (c)

NCC 2022 HP, 4.2.11

AS 3600:2018, 4.3.1 (c)

AS 3600:2018, 17.1.3

Concrete Mix Specification


  • Normal-Class
  • General use[1]
  • Standard compressive strength[2]
  • Special-Class[3]
  • Customised (e.g. severe environments)


Special Class Concrete Specification REQUIREMENTS


NCC 2022 V1


AS 1379:2007, 1.5.4

AS 1379:2007, 1.5.4 (a)

AS 1379:2007, 1.5.4 (b)

AS 1379:2007, 1.5.4 (c)

AS 1379:2007, 1.5.4 (i)

AS 1379:2007, 1.5.4 (ii)

AS 1379:2007, 1.5.4 (iii)

AS 1379:2007, 1.5.4

AS 1379:2007, 1.5.4

AS 1379:2007, 1.5.4 (A)

AS 1379:2007, 1.5.4 (B)

AS 1379:2007, B1

Normal Class Concrete Specification REQUIREMENTS


NCC 2022 V1


AS 1379:2007, 1.5.3.1 (a)

AS 1379:2007, 1.5.3.1 (c)

AS 1379:2007, 1.5.3.1 (b)

AS 1379:2007, 1.5.3.1 (f)

AS 1379:2007, 1.5.3.1 (e)

AS 1379:2007, 1.5.3.1 (d)

AS 1379:2007, 1.5.3.2 (c)

AS 1379:2007, 1.5.3.2 (d)

AS 1379:2007, 1.5.3.2 (e)

AS 1379:2007, 1.5.3.2 (f)

AS 1379:2007, 1.5.3.2 (a)

AS 1379:2007, 1.5.3.2 (b)

AS 1379:2007, 1.5.1 (a) (ii)

AS 1379:2007, 1.5.1 (a) (i)

Informative

Strength


  • Characteristic Compressive Strength[1]
  • Exceeded by 95% of concrete test results for a given mix


Concrete Strength RULES


NCC 2022 V1


AS 1379:2007, 5.3.1

AS 1379:2007, 5.3.3

AS 1379:2007, 5.3.4

  • 28-Day Characteristic StrengthAS 1379:2007, 5.3.1
  • Compressive Strength tested to AS 1012
  • Flexural/Tensile Strength assessed via an equivalent mean compressive strength requiring:
  • Initial relationship established, 1 sample from 3 different compressive strength grades
  • Ongoing monitoring with 2 samples per production interval; re-establish if needed
  • ≥ 2 Compressive & ≥ 3 Flexural or Tensile specimens cured & tested to AS 1012 for each every sample
  • Compliance
  • Concrete complies if AS 1379 requirements for sampling, testing & assessment are metAS 1379:2007, 5.3.3
  • Non-compliant concrete may be accepted ifAS 1379:2007, 5.3.4
  • Supplier has a third-party audited QC system showing low results are within random variation
  • Supplier demonstrates non-compliance was a specific interval issue with identified causes, allowing other concrete to comply
  • Mutually acceptable alternative methods prove the structure's fitness for purpose
  • Allows acceptance of In-place Concrete ONLY, not compliance with the specified strength grade

Concrete Strength Grades of Typical Building Elements


NCC 2022 V1


AS 1379:2007, 1.3.7

  • Characteristic Compressive StrengthAS 1379:2007, 1.3.7
  • Exceeded by 95% of concrete test results for a given mix

Abrasion


  • Hardness of Concrete required to resist Abrasion[1]


Concrete ABRASION


NCC 2022 V2


All Building Classes


NCC 2022 Part 4.2.10 [2019: 3.2.3.1]


May 2023



AS 3600:2018, 4.6

NCC 2022 HP, 4.2.10

  • Concrete must comply with NCCAS 3600:2018, 4.6
  • For locations susceptible to abrasion from vehicular traffic, the compressive strength of the Concrete must surpass the values outlined in the table belowNCC 2022 HP, 4.2.10

AS 3600:2018, 4.6

Slab Edge Rebate

Mixing & Transportation


  • ≤1½ hours complete discharge from concrete truck upon cement hydration unless a retarder is used[1]


Water, Admixture & Additives in Concrete Mix RULES


NCC 2022 V1


AS 1379:2007, 4.2.3

AS 1379:2007, 4.2.4

  • Water AdditionAS 1379:2007, 4.2.3
  • Only the supplier can add water to a mixed batch, within 75 minutes or 80% of the agreed discharge time, or whichever is greater
  • Operate the mixer at rated speed for at ≥ 30 revolutions for uniformity
  • Re-assess specified slump after remixing
  • Document the added water quantity if adjusted during discharge
  • Ensure the water-cement ratio remains within specified tolerances
  • Admixture & Material AdditionAS 1379:2007, 4.2.4
  • Only the supplier can add admixtures or other materials before batch discharge is complete
  • All additions must follow the material supplier's specifications
  • Operate the mixer at rated speed for ≥ 30 revolutions to re-establish uniformity, & record the type & quantity on the identification certificate
  • If the addition aims to modify slump, re-assess slump after remixing

Concrete Mix RULES


NCC 2022 V4


All Building Classes


NCC 2022, 4.2.10 [2019 3.2.3.1]



May 2023



NCC 2022 HP, 4.2.10

  • Concrete to comply with NCCNCC 2022 HP, 4.2.10
  • Mixing & Delivery
  • ≤ 1 ½ hrs complete discharge from Concrete truck upon Cement hydration unless a retarder is used
  • Compaction by vibration
  • To remove air pockets
  • Improve contact with Reinforcement & Formwork
  • Enhance durability
  • Avoid over-vibrating
  • Slab Edges
  • Proper finishing & curing of edges improves resistance to moisture damage
  • Chemical Curing
  • Determine if surface finish adhesive to be used is compatible with chemical curing methods

NCC 2022 HP, 4.2.10

  • ≤1½ hours complete discharge from concrete truck upon cement hydration unless a retarder is usedNCC 2022 HP, 4.2.10

Concrete Form Finish Classes

Redirecting... (5)
Please wait while we redirect you to the correct page.