Floor finish or Membrane Protection
Finished Level
Structural Substrate
Membrane
Membrane
Flashing
Sealant
Plinth provided
for all Penetrations
Compatible
Sealant
Clamp
Top of Membrane / Collar
All Building Classes
NCC 2022 F1D5, H2D8, & HP10.2 [2019 F1.4, 3.8.1.2, 3.8.1.3]
May 2023
M
Clearance
Overlap
Sealant wipe over fixings
Sealant Bead
Collar
Finished Level
≥ 1:100AS 4654.2:2012, 2.5.2
Fall
M
M
M
M
M
M
Floor System
M
M
M
All Building Classes
NCC 2022 F1D5, H2D8, & HP10.2 [2019 F1.4, 3.8.1.2, 3.8.1.3]
May 2023