Vertical Penetration with Collar Building Codes & Rules


- Vertical Penetrations Tools™ simplifies the National Construction Code (NCC) with interactive graphics, including deemed to comply & best practices.


Floor finish or Membrane Protection

Finished Level

Structural Substrate

Membrane

Membrane

Flashing

AS 4654.2:2012, 2.8.4

≥ 75AS 4654.2:2012, 2.8.4

Sealant

Plinth provided

for all Penetrations

Compatible

Sealant

Clamp

Top of Membrane / Collar

Membrane / Collar Height


  • Height varies with wind class[1][2]


Membrane Height RULES


NCC 2022 V4


All Building Classes


NCC 2022 F1D5, H2D8, & HP10.2 [2019 F1.4, 3.8.1.2, 3.8.1.3]


May 2023



AS 4654.2:2012, 2.8.1.1

AS 4654.2:2012, A

NCC 2022 Vol 1, F1D5

NCC 2022 Vol 2, H2D8

NCC 2022 HP, 10.2.1

AS 4654.2:2012, 2.8.1.1

AS 4654.2:2012, A

M

AS 4654.2:2012, 2.8.4

≥ 75AS 4654.2:2012, 2.8.4

Clearance

AS 4654.2:2012, 2.8.4

≥ 10AS 4654.2:2012, 2.8.4

Overlap

Sealant wipe over fixings

Sealant Bead

Collar

Finished Level

AS 4654.2:2012, 2.5.2

≥ 1:100AS 4654.2:2012, 2.5.2

Fall

M

M

M

M

M

M

Floor System

M

M

M

Vertical Penetration


  • Sealed[1]
  • Collar fixed to the substrate
  • Membrane turns up & supported by Collar


Vertical Penetration RULES


NCC 2022 V1


All Building Classes


NCC 2022 F1D5, H2D8, & HP10.2 [2019 F1.4, 3.8.1.2, 3.8.1.3]


May 2023



AS 4654.2:2012, 2.8.4

NCC 2022 Vol 1, F1D5

NCC 2022 Vol 2, H2D8

NCC 2022 HP, 10.2.1

AS 4654.2:2012, 2.8.4

AS 4654.2:2012, 2.8.4

Redirecting... (5)